To turn your grid connect solar power system ON:
Switch ON in the sequence: 1, 2, 3. Do not wait too long between switching 2 and 3; otherwise the inverter will perceive this as a fault condition.


After the system is switched ON, the inverter will run through a testing and initializing process. It will begin correct operation when the green “Operation” indicator lights up, located on its front panel.
Confirm correct GCS system operation by reading the generated voltage and power values from the inverter’s LCD user menu, located on the front panel of the SMA Sunny Boy inverter.
To turn your grid connect solar power system OFF:
Switch ON in the sequence: 1, 2, 3. Do not wait too long between switching 2 and 3; otherwise the inverter will perceive this as a fault condition.